Mushing District Phase I Schedule
This is the planned schedule for installation of the Mushing District and arch.
Schedule Date |
Milestone |
January 2019 |
Kick-off official fundraising campaign. |
October 2019 |
Initiate all construction documents. |
September 2020 |
Secure building permit. |
January 2021 |
Negotiate contract for fabrication and construction of arch. |
February 2021 |
Award fabrication contract |
February 2021 |
Solicit bids for street work |
March 2021 |
Award & start construction of foundations, sidewalks, & concrete work. |
October 2021 |
Complete construction of arch. |
October 2021 |
Complete interior work on Mushing Hall of Fame. |
November 2021 |
Manufacture and engrave bronze disks. |
February 2022 |
Grand dedication of the arch at 2022 Fur Rondy Celebration. |
May 2022 |
Install banners, plaques, interpretive signage, and bronze disks. |
September 2022 |
Completion of Phase I |