Mushing District Phase I Schedule

This is the planned schedule for installation of the Mushing District and arch.

Schedule Date

 Milestone

January 2019

 Kick-off official fundraising campaign.

October 2019

Initiate all construction documents.

September 2020

Secure building permit.

January 2021

Negotiate contract for fabrication and construction of arch.

February 2021

Award fabrication contract

February 2021

Solicit bids for street work

March 2021

Award & start construction of foundations, sidewalks, & concrete work.

October 2021

Complete construction of arch.

October 2021

Complete interior work on Mushing Hall of Fame.

November 2021

Manufacture and engrave bronze disks.

February 2022

Grand dedication of the arch at 2022 Fur Rondy Celebration.

May 2022

Install banners, plaques, interpretive signage, and bronze disks.

September 2022

 Completion of Phase I